Construction Update

Updated: Apr. 4, 2007

ANDERSON WING

Beginning Monday, April 16 the Anderson wing elevators will not be accessible on the first floor. This closure will last for approximately four weeks. There will be a temporary egress around the elevator lobby. Employees, patients and visitors will need to use the Pool elevators to access the second and third floor of the Anderson wing. Signs will be posted.

Dietary department construction began last week.

KASYCH

Painting and case work has begun on the fourth floor. Drywall, electrical, and plumbing work continue throughout the building. PPL is still working on the alternate feed for the new tower.

SITE RENOVATIONS ON CAMPUS

Crews will be adjusting the grade and creating a berm in parking lot 4A in preparation for the upcoming entrance changes. Work continues in the detention basins at the front and rear of the campus. Permanent trench restorations, curbing and sidewalk will occur in parking lots 4, 5, & 6 over the next month. Topsoil and grass seeding will occur next week near the Bridge, 1250 MOB and the 1250 surface lot (weather permitting.)

FRONT WEST PARKING DECK

Bulk excavation continues and footer/foundation wall installation has started.

EMERGENCY ROOM RENOVATION

New, easy to read exterior signs are in place. Lighting has been installed in the covered tunnel to the ED entrance. Excavation for the new building's micro piles and footers continues.

HIGHWAY IMPROVEMENT PROJECT

Crews will begin to dig a detention pond along Cedar Crest Blvd south of Fish Hatchery Rd.

Updated: Mar. 28, 2007

ANDERSON WING

Beginning Saturday, April 14 (tentative date) the Anderson wing elevators will not be accessible on the first floor. This closure will last for approximately four weeks. There will be a temporary egress around the elevator lobby. Employees, patients and visitors will need to use the Pool elevators to access the second and third floor of the Anderson wing. Signs will be posted.

Departments have been moved out of the first floor on the west side of the building and the volunteer office and library areas have been modified to accommodate construction. Dietary department construction will begin this week.

KASYCH

Painting and case work has began on the fourth floor. Drywall, electrical, and plumbing work continue throughout the building. PPL is still working on the feed to the new building.

SITE RENOVATIONS ON CAMPUS

Crews will be adjusting the grade and creating a berm in parking lot 4A in preparation for the upcoming entrance changes. Work continues in the detention basins at the both the front and rear of the campus. Permanent trench restorations will occur in parking lots 4, 5, & 6 over the next week. This will require equipment and material deliveries in the trench locations.

FRONT WEST PARKING DECK

Bulk excavation continues.

EMERGENCY ROOM RENOVATION

New, easy to read exterior signs are in place. Lighting has been installed in the covered tunnel to the ED entrance. Excavation for the new building's micro piles and footers continues.

HIGHWAY IMPROVEMENT PROJECT

Crews will begin to dig a detention pond along Cedar Crest Blvd south of Fish Hatchery Rd.

Updated: FEB. 28, 2007

ANDERSON WING

Work will begin on the third floor in the area of the sleep rooms; some construction noise should be expected in the next few weeks.

EMERGENCY ROOM RENOVATIONS

Water line installation and relocation continues. Portions of the parking lots near the emergency room will be affected for short periods of time as the work progresses.

A visitor assistant is posted at the emergency room entrance from 6 A.M. to 2 A.M. (20 hours) - seven days a week to assist people dropping off patients and help with parking. When the ER lot is full parking passes will be given to visitors for a lot close by the ED.

CENTER FOR ADVANCED HEALTH CARE BUILDING

Tenants will begin to move into the building beginning with the CAT scan
department of Lehigh Valley Diagnostic Imaging (LVDI) in April 07, other
tenants will follow through the end of 2007.

PEDESTRIAN BRIDGE

The pedestrian bridge will open in April 07 with the opening of LVDI CAT scan.

CANCER CENTER TEMPORARY ENTRANCE CLOSING

The new permanent entrance to the cancer center will open by the end of this
week. The new entrance is also the vestibule of the pedestrian bridge on the
cancer center side. The temporary entrance (with the blue canopy) will close.

SITE RENOVATIONS ON CAMPUS - all outside work is weather permitting

  • Parking deck construction in front of the Anderson wing continues.
  • Follow fencing and signs for all pedestrian walkways.
  • Excavation work continues in the detention basin on the south side of the campus.
  • Storm and water line installation continues along the Anderson and Kasych buildings.

Updated: Jan. 25, 2007

EMERGENCY ROOM RENOVATIONS

Work will begin in early February to expand the emergency room. The first phase will be to fence off a portion of the emergency parking lot and establish a new covered walk way into the ED.

KASYCH PAVILION

Crews are working to finish exterior windows and glazing. Interior work includes continuation of mechanical/electrical/plumbing rough-ins. Stud work and dry wall work have begun on levels one, two and three. Work has begun on elevator cars and platforms.

SITE RENOVATIONS ON CAMPUS

The campus ring road near the Kasych Pavilion will close on the following dates in order to install utilities:

  • Saturday January 27 from 8 a.m. to 8 p.m.
  • Saturday February 2 from 8 a.m. to 8 p.m.

Traffic will be routed around the back of the hospital during the closures.

Please slow down, watch for signs and traffic control.

Storm and water line installation continues along the Anderson and Kasych buildings.

Excavation work continues in the detention basin on the south side of the campus.

PATIENT AND VISITOR PARKING JUST GOT EASIER

Today, we have more parking available than before and there's more to come. Patients and visitors may use the 5-level parking deck with free shuttle service to the front entrance and the 2-level deck in front
of the hospital.

HIGHWAY IMPROVEMENTS (CEDAR CREST BLVD)

Starting in February construction will begin along Cedar Crest Blvd., beginning at Fish Hatchery Road. The first stage will be tree trimming and utility pole relocations along Fish Hatchery Road. Future work will include adding turning lanes, updating signs, enhancing storm drainage and re-paving. The projected completion of the construction is November 2007.


Updated: Thursday, Nov. 9, 2006

Detention Area

Earth work and storm water piping install to continue at the berm this week.

 


Parking Decks

During the next two weeks, curbing will be installed around the surface parking areas for both the five-story deck and the east front deck. There will be some lane closures during this time and traffic control will be in place. Please proceed carefully and watch for flagman and signs. Please be advised that all pedestrian traffic to the five-story parking deck has shifted to the covered walkway.

Kasych Pavilion

Installation of the curtain wall of windows on the first floor will start this week.

Updated: Wed., October 11, 2006

Special Announcement

On Saturday, Oct. 21 parking lot 4A (employee stone lot to the left of the main entrance) will be closed for entire day for re-grading. Then on Saturday, Oct. 28 the same lot will close for re-striping, weather permitting.

Detention Area

Soil compacting work will continue next week.

Pedestrian Bridge

Interior work continues on the ceiling and utilities are being installed.

Parking Lot

Surface parking work continues around the five story parking deck.

East Parking Deck

Light pole installation and concrete work continue. The deck is scheduled to open in late December 2006.

Kasych Pavilion

Installation of windows, roofing and interior work continues.


If you have any questions, call 610-402-CARE.

 


Updated: Wed., Sept. 27, 2006

AMBULANCE DRIVE

On Thurs. Sept. 28, the delivery of a boiler will cause one lane of the Ambulance Drive to be closed. Traffic control will be in place.

SHUTTLE CHANGE

The shuttle pickup location for patients, visitors and colleagues using the parking deck along Cedar Crest Blvd. has been shifted to The Center for Advanced Health Care canopy area.

SITE WORK

Phase 3 of the site work has begun on both the east and south sides of the campus. It includes creating a new retention basin, storm water drainage and significant landscaping. Use caution in these areas.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

Flag men are in place as ring road traffic is reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Crews are installing the bridge's exterior glass panels.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a 'green,' or environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: Wed., Sept. 20, 2006

SITE WORK

Phase 3 of the site work begins today, it includes creating a new retention basin, storm water drainage and significant landscaping.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or
environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: September 13, 2006

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior stud installation has also begun.

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or environmentally friendly building.

Updated: August 23, 2006

****MAIN ENTRANCE WILL CLOSE ON THURSDAY AT 8:30 P.M.*****

The road leading to the main entrance will close on Thurs., Aug. 24 at 8:30p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27.

During this time, Jaindl Pavilion patients will be discharged from the MRI exit. All other patients will be discharged from the Anderson wing door near the medical library.

Click here to download a map of the road closures

EAST PARKING DECK

The installation of precast concrete panels will conclude this week. Mechanical works continues.

PEDESTRIAN BRIDGE

As crews begin painting the bridge that connects The Center for Advanced Health Care with the Cancer Center, lane closures will occur. Traffic control will be in place.

THE CENTER FOR ADVANCED HEALTH CARE

Topsoil, grading and pavement preparation is complete.

KASYCH FAMILY PAVILION

Window, precast panel and mechanical rough-in installation continues.

If you have any questions, call 610-402-CARE.

Updated: August 9, 2006

MAIN ENTRANCE

This week, the median divider will be set between the front entrance drop-off lanes. The remaining curbing will also be poured this week.

The road leading to the main entrance will be closed on Thurs., Aug. 24 at 8:30 p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27. More details, including discharging patients during this process, will be coming next week.

EAST PARKING DECK

The installation of precast concrete panels continues on the first of two new
parking decks in front of the hospital. Through December, 284 panels weighing
5,761 tons will be delivered to the site. Traffic control will be in place as
trucks enter and exit the site. Use caution when driving near this area.

PEDESTRIAN BRIDGE

Precast concrete panels will be placed and the bridge∞s walking surface will
be poured this week.

THE CENTER FOR ADVANCED HEALTH CARE

The curb, sidewalk, grading and pavement preparation will continue being
placed this week.


Wed., Aug. 2, 2006


 EAST PARKING DECK

The installation of precast concrete panels has begun on the first of two new parking decks in front of the hospital. Through December, traffic control will be in place as 284 panels, weighing 5,761 tons, are delivered to the site.

PEDESTRIAN WALKWAY

Following construction of the bridge's staircases, crews will resume installing exterior panels to the bridge connecting the Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Watch for lane closures along the ring road during this time. Traffic control will be in place.

KASYCH FAMILY PAVILION

Installation of window sills has begun in preparation for window installation beginning in mid-August.

DESIGNATED SMOKING AREAS

Smoking is not permitted in front of the hospital and we will become totally smoke-free on Jan. 1, 2007. Direct smokers to


 


Parking Decks

During the next two weeks, curbing will be installed around the surface parking areas for both the five-story deck and the east front deck. There will be some lane closures during this time and traffic control will be in place. Please proceed carefully and watch for flagman and signs. Please be advised that all pedestrian traffic to the five-story parking deck has shifted to the covered walkway.

Kasych Pavilion

Installation of the curtain wall of windows on the first floor will start this week.

Updated: Wed., October 11, 2006

Special Announcement

On Saturday, Oct. 21 parking lot 4A (employee stone lot to the left of the main entrance) will be closed for entire day for re-grading. Then on Saturday, Oct. 28 the same lot will close for re-striping, weather permitting.

Detention Area

Soil compacting work will continue next week.

Pedestrian Bridge

Interior work continues on the ceiling and utilities are being installed.

Parking Lot

Surface parking work continues around the five story parking deck.

East Parking Deck

Light pole installation and concrete work continue. The deck is scheduled to open in late December 2006.

Kasych Pavilion

Installation of windows, roofing and interior work continues.


If you have any questions, call 610-402-CARE.

 


Updated: Wed., Sept. 27, 2006

AMBULANCE DRIVE

On Thurs. Sept. 28, the delivery of a boiler will cause one lane of the Ambulance Drive to be closed. Traffic control will be in place.

SHUTTLE CHANGE

The shuttle pickup location for patients, visitors and colleagues using the parking deck along Cedar Crest Blvd. has been shifted to The Center for Advanced Health Care canopy area.

SITE WORK

Phase 3 of the site work has begun on both the east and south sides of the campus. It includes creating a new retention basin, storm water drainage and significant landscaping. Use caution in these areas.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

Flag men are in place as ring road traffic is reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Crews are installing the bridge's exterior glass panels.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a 'green,' or environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: Wed., Sept. 20, 2006

SITE WORK

Phase 3 of the site work begins today, it includes creating a new retention basin, storm water drainage and significant landscaping.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or
environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: September 13, 2006

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior stud installation has also begun.

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or environmentally friendly building.

Updated: August 23, 2006

****MAIN ENTRANCE WILL CLOSE ON THURSDAY AT 8:30 P.M.*****

The road leading to the main entrance will close on Thurs., Aug. 24 at 8:30p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27.

During this time, Jaindl Pavilion patients will be discharged from the MRI exit. All other patients will be discharged from the Anderson wing door near the medical library.

Click here to download a map of the road closures

EAST PARKING DECK

The installation of precast concrete panels will conclude this week. Mechanical works continues.

PEDESTRIAN BRIDGE

As crews begin painting the bridge that connects The Center for Advanced Health Care with the Cancer Center, lane closures will occur. Traffic control will be in place.

THE CENTER FOR ADVANCED HEALTH CARE

Topsoil, grading and pavement preparation is complete.

KASYCH FAMILY PAVILION

Window, precast panel and mechanical rough-in installation continues.

If you have any questions, call 610-402-CARE.

Updated: August 9, 2006

MAIN ENTRANCE

This week, the median divider will be set between the front entrance drop-off lanes. The remaining curbing will also be poured this week.

The road leading to the main entrance will be closed on Thurs., Aug. 24 at 8:30 p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27. More details, including discharging patients during this process, will be coming next week.

EAST PARKING DECK

The installation of precast concrete panels continues on the first of two new
parking decks in front of the hospital. Through December, 284 panels weighing
5,761 tons will be delivered to the site. Traffic control will be in place as
trucks enter and exit the site. Use caution when driving near this area.

PEDESTRIAN BRIDGE

Precast concrete panels will be placed and the bridge∞s walking surface will
be poured this week.

THE CENTER FOR ADVANCED HEALTH CARE

The curb, sidewalk, grading and pavement preparation will continue being
placed this week.


Wed., Aug. 2, 2006


 EAST PARKING DECK

The installation of precast concrete panels has begun on the first of two new parking decks in front of the hospital. Through December, traffic control will be in place as 284 panels, weighing 5,761 tons, are delivered to the site.

PEDESTRIAN WALKWAY

Following construction of the bridge's staircases, crews will resume installing exterior panels to the bridge connecting the Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Watch for lane closures along the ring road during this time. Traffic control will be in place.

KASYCH FAMILY PAVILION

Installation of window sills has begun in preparation for window installation beginning in mid-August.

DESIGNATED SMOKING AREAS

Smoking is not permitted in front of the hospital and we will become totally smoke-free on Jan. 1, 2007. Direct smokers to


 

 


Parking Decks

During the next two weeks, curbing will be installed around the surface parking areas for both the five-story deck and the east front deck. There will be some lane closures during this time and traffic control will be in place. Please proceed carefully and watch for flagman and signs. Please be advised that all pedestrian traffic to the five-story parking deck has shifted to the covered walkway.

Kasych Pavilion

Installation of the curtain wall of windows on the first floor will start this week.

Updated: Wed., October 11, 2006

Special Announcement

On Saturday, Oct. 21 parking lot 4A (employee stone lot to the left of the main entrance) will be closed for entire day for re-grading. Then on Saturday, Oct. 28 the same lot will close for re-striping, weather permitting.

Detention Area

Soil compacting work will continue next week.

Pedestrian Bridge

Interior work continues on the ceiling and utilities are being installed.

Parking Lot

Surface parking work continues around the five story parking deck.

East Parking Deck

Light pole installation and concrete work continue. The deck is scheduled to open in late December 2006.

Kasych Pavilion

Installation of windows, roofing and interior work continues.


If you have any questions, call 610-402-CARE.

 


Updated: Wed., Sept. 27, 2006

AMBULANCE DRIVE

On Thurs. Sept. 28, the delivery of a boiler will cause one lane of the Ambulance Drive to be closed. Traffic control will be in place.

SHUTTLE CHANGE

The shuttle pickup location for patients, visitors and colleagues using the parking deck along Cedar Crest Blvd. has been shifted to The Center for Advanced Health Care canopy area.

SITE WORK

Phase 3 of the site work has begun on both the east and south sides of the campus. It includes creating a new retention basin, storm water drainage and significant landscaping. Use caution in these areas.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

Flag men are in place as ring road traffic is reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Crews are installing the bridge's exterior glass panels.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a 'green,' or environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: Wed., Sept. 20, 2006

SITE WORK

Phase 3 of the site work begins today, it includes creating a new retention basin, storm water drainage and significant landscaping.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior wall stud installation is ongoing.

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or
environmentally friendly building,

If you have any questions, call 610-402-CARE.

Updated: September 13, 2006

PEDESTRIAN BRIDGE

For the next two weeks, ring road traffic will be reduced to two lanes underneath the bridge connecting The Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. During this time, crews will install the bridge's exterior glass panels. Traffic control will be in place.

EAST PARKING DECK

The installation of precast concrete panels is complete. Crews are applying concrete washes and will soon begin installing lighting fixtures, the sprinkler system, handrails and safety grates.

KASYCH FAMILY PAVILION

Installation of windows, roofing, precast concrete panels and mechanical systems continues. Interior stud installation has also begun.

THE CENTER FOR ADVANCED HEALTH CARE

Inside, tenants and architects are collaborating to design workspace areas. The LEED (Leadership in Energy and Environmental Design) commissioning process continues to determine if the structure can officially be called a "green," or environmentally friendly building.

Updated: August 23, 2006

****MAIN ENTRANCE WILL CLOSE ON THURSDAY AT 8:30 P.M.*****

The road leading to the main entrance will close on Thurs., Aug. 24 at 8:30p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27.

During this time, Jaindl Pavilion patients will be discharged from the MRI exit. All other patients will be discharged from the Anderson wing door near the medical library.

Click here to download a map of the road closures

EAST PARKING DECK

The installation of precast concrete panels will conclude this week. Mechanical works continues.

PEDESTRIAN BRIDGE

As crews begin painting the bridge that connects The Center for Advanced Health Care with the Cancer Center, lane closures will occur. Traffic control will be in place.

THE CENTER FOR ADVANCED HEALTH CARE

Topsoil, grading and pavement preparation is complete.

KASYCH FAMILY PAVILION

Window, precast panel and mechanical rough-in installation continues.

If you have any questions, call 610-402-CARE.

Updated: August 9, 2006

MAIN ENTRANCE

This week, the median divider will be set between the front entrance drop-off lanes. The remaining curbing will also be poured this week.

The road leading to the main entrance will be closed on Thurs., Aug. 24 at 8:30 p.m. for paving. Traffic will be directed into the valet lot where patients and visitors can be dropped off. The new road will open to traffic on or before Sun., Aug 27. More details, including discharging patients during this process, will be coming next week.

EAST PARKING DECK

The installation of precast concrete panels continues on the first of two new
parking decks in front of the hospital. Through December, 284 panels weighing
5,761 tons will be delivered to the site. Traffic control will be in place as
trucks enter and exit the site. Use caution when driving near this area.

PEDESTRIAN BRIDGE

Precast concrete panels will be placed and the bridge∞s walking surface will
be poured this week.

THE CENTER FOR ADVANCED HEALTH CARE

The curb, sidewalk, grading and pavement preparation will continue being
placed this week.


Wed., Aug. 2, 2006


 EAST PARKING DECK

The installation of precast concrete panels has begun on the first of two new parking decks in front of the hospital. Through December, traffic control will be in place as 284 panels, weighing 5,761 tons, are delivered to the site.

PEDESTRIAN WALKWAY

Following construction of the bridge's staircases, crews will resume installing exterior panels to the bridge connecting the Center for Advanced Health Care with the John and Dorothy Morgan Cancer Center. Watch for lane closures along the ring road during this time. Traffic control will be in place.

KASYCH FAMILY PAVILION

Installation of window sills has begun in preparation for window installation beginning in mid-August.

DESIGNATED SMOKING AREAS

Smoking is not permitted in front of the hospital and we will become totally smoke-free on Jan. 1, 2007. Direct smokers to



This page last updated 2/19/08 09:50 PM
ARTICLE TOOLS:

email this article to a friend print this article    Del.icio.us   Stumble It!






hon cod ©2008 Lehigh Valley Hospital and Health Network
LVH Info Line: 610-402-CARE
Cedar Crest & I-78, P.O. Box 689, Allentown, PA 18105-1556

Lehigh Valley Hospital has campuses in Allentown and Bethlehem, Pa. and serves the Pennsylvania communities of Easton, Doylestown, Quakertown, Hazelton, Lehighton, Perkasie, Pottstown, Pottsville, Reading, Scranton, Wilkes Barre, Stroudsburg, and the Poconos and also Phillipsburg and Flemington, N.J., and western New Jersey. You don't have to travel to Philadelphia or New York for quality health care.

 
Increase the Size of Text by clicking here. Descrease the Size of Text by clicking here Email this story to family and friends. Print this story formatted for your printer.